Lease to opening
The order of work, with what we need and what you get
Dates belong to your landlord, your contractor and the city. The order does not change.
- 01Before you sign
Step 1: Walk the space
We read the panel and the meter, and measure what is there against your equipment and lighting plans.
You send: the address, the lease draft if you have one, and your equipment list
You get: a short note on what the service can carry and what the landlord has to approve
- 02Drawings
Step 2: Price from the plans
We bid from drawings, or from our marked-up sketch when drawings are not done.
You send: your architect's plans, or the layout you have so far
You get: a written bid that lists what is in it and what is left out
- 03Permit
Step 3: Pull the permit
We apply for the electrical permit for our scope and agree with your contractor who calls each inspection.
You send: the landlord's approval where the lease asks for it
You get: the permit number and the inspection order
- 04Open walls
Step 4: Rough-in
Boxes, cable and conduit go in before the board and the ceiling close.
You send: access to the space once the framing stands
You get: a rough-in inspection, booked before any board goes up
- 05Trim
Step 5: Fixtures and equipment
Fixtures, devices and your equipment get connected and tested.
You send: fixtures and equipment on site, and the name of whoever installs the sign
You get: a working space, and a printed schedule of what each breaker feeds
- 06Handover
Step 6: Final inspection
We book the final inspection and fix what the inspector lists.
You send: the date the city or landlord needs the space ready
You get: the signed inspection and marked-up plans for your contractor
- 07Day one
Step 7: Opening week
We stay on the phone while your staff learn the panel and the controls.
You send: the name of your opening-day manager
You get: one number to call if a circuit does not work
What slows an opening
Four things that move a date
Utility work
A new or larger service can take the utility longer than the build, so we ask at the walk.
Landlord approvals
A change to the service or a shared panel waits on written approval from the landlord.
Plan review
The city's review of the plans sets the first date nobody else controls.
Long-lead items
Special fixtures and equipment can arrive after the walls are closed, and we plan the rough-in for them.
Start with the walk